Description: 9-mile, controlled-acess toll road bypassing the Dallas central business district near the Trinity River levee. Initially, six and four lanes will be constructed, with the ultimate facility being six lanes.
Status: Archaeological work is completed. The NTTA is working with its partners to obtain environmental clearance.
Estimated Cost Range for eight alternative alignments: $1.1 billion to $2.1 billion (Estimates based on a modified alternative, subject to change as design progresses and economic conditions change.)
Estimated Construction Date: To be determined
Date Updated: October 2009
Source: http://www.ntta.org/AboutUs/Projects/TrinityParkway.htm